How to install a prehung interior door yourself: step by step

Short answer

To install a prehung interior door, follow the 16 steps below, from “Confirm the opening and the unit match” to “Quality check before casing”. Difficulty 3 of 5; for a first-timer, plan on about half a day. Read the “Stop here” box below before step 1.

Quick review by a licensed contractor on Oct 7, 2026. This is not a certification. Follow product labels where they differ.

Shims, plumb on the hinge side, 1/8" gap. The whole job is one idea: get the hinge jamb dead plumb and perfectly straight, and the rest follows.

Difficulty 3 of 5 · about half a day · careful

Stop here

Plumb the hinge side first and shim behind every hinge. A door hung out of plumb never closes right, and the casing hides the fix — so get it right before the casing goes on. Stop and call a carpenter if: the rough opening is too small and would have to be cut wider (framing changes in a load-bearing wall are not DIY); the header or studs are cracked, rotten, or badly bowed; the floor is more than about 1/2" out of level across the opening; or the door is a fire-rated or exterior unit. In a building from before 1978, treat the old painted casing and jamb as lead paint unless a test says otherwise: use lead-safe practices (pry, do not sand, keep it wet, bag the debris), or hire an EPA lead-safe certified firm.
See it in your own room — free

Photo of your room, the look you pick, then this guide with the materials counted for your room.

What you need

  • Prehung interior door unit (correct width, height, jamb width, and hand)
  • Composite or cedar shims
  • 2-1/2" to 3" construction or trim screws (top hinge into the stud)
  • 2-1/2" finish nails (15 or 16 gauge) for the jamb
  • Low-expansion door and window foam
  • Passage or privacy lever set (one per replaced door)

Tools

  • 6 ft level (the single most important tool here) — A 4 ft level plus a straight board works if you cannot get a 6 ft one.
  • Drill/driver
  • Hammer and nail set
  • Utility knife (trim shims flush)
  • Wood chisel (only if you have to adjust a hinge mortise)
  • Finish nailer (15/16 ga) with compressor, or cordless — $35–55/day (Los Angeles prices; yours scale with your area). You will want it again for casing and baseboards — rent for the whole trim weekend.
  • Pry bar and a block of wood (removing the old jamb)

Step by step

  1. Step 1 of 16

    Confirm the opening and the unit match

    Confirm the opening and the unit match

    Put your opening notes next to the box: width, height, jamb width, hand. The rough opening should be about 2" wider and 2-1/2" taller than the door slab; the door unit's sheet has the exact numbers. Unwrap one unit and check it is not damaged or twisted before you start anything.

  2. Step 2 of 16

    Leave the shipping braces on the door

    Leave the shipping braces on the door

    The factory blocks or staples that hold the door closed inside the jamb keep the frame in shape while you set it. Leave them on until the hinge jamb is tacked (step 8), then take them off so the door can swing.

  3. Step 3 of 16

    Clean out the opening and check the floor again

    Clean out the opening and check the floor again

    No nails, no drywall lumps on the stud faces. Re-check the floor across the opening with a level. If it is out, trim the bottom of the jamb leg on the high side by the amount you measured before the unit goes in, so the head can come level. On a floating floor the jamb legs can stand on it, but never nail or screw through the floor.

    Ready to set the door?

    • Finished floor is down in the room
    • Opening is stripped to framing, clean and flat
    • Door unit width, height, jamb width, and hand all match your notes
    • You have shims, a 6 ft level, and a nailer or screws on hand
    • You know which side of the floor is high, and that jamb leg is trimmed to match
  4. Step 4 of 16

    Dry-fit the unit in the opening

    Dry-fit the unit in the opening

    Slide it in from the side the door swings toward. You want about 1/4" of play between the jamb and the framing on each side and about 1/2" over the head jamb — that is your shimming room. If it will not go in without force, the opening is too small; do not trim the framing yourself.

  5. Step 5 of 16

    Set the jamb flush with the finished wall

    Set the jamb flush with the finished wall

    The face of the jamb should sit flush with the drywall on both sides, so the casing lies flat. If the wall is thicker, add a jamb extension rather than letting the casing rock.

  6. Step 6 of 16

    Plumb the hinge jamb first — both directions

    Plumb the hinge jamb first — both directions

    Hold the 6 ft level on the face of the hinge leg and plumb it, then on the edge of the same leg and plumb it again. Both readings matter: face plumb keeps the door from swinging on its own, edge plumb keeps it from rubbing the stop.

  7. Step 7 of 16

    Shim behind every hinge

    Shim behind every hinge

    Slide a pair of shims (two tapered shims pointing opposite ways) in from both sides directly behind each hinge, plus one pair near the top and one near the bottom. Tap them until the level still reads plumb and the level shows no bow along the leg.

  8. Step 8 of 16

    Tack the hinge jamb, and send one long screw into the stud

    Tack the hinge jamb, and send one long screw into the stud

    Drive one nail through the jamb at each shim pair — tack only, do not set them yet. Then remove one factory screw from the top hinge and replace it with a 2-1/2" to 3" construction or trim screw that reaches the stud — that screw is what keeps the door from sagging. Snug only: stop the moment the reveal changes. Now take off the shipping braces.

  9. Step 9 of 16

    Set the head jamb level

    Set the head jamb level

    With the hinge side tacked, check the head jamb with the level. Bring it level by shimming under the latch leg or nudging that leg, never by loosening the hinge side. If the latch leg is too long for the head to come level, pull its tacks and trim it rather than forcing it, and never so the door drags.

  10. Step 10 of 16

    Work the latch side to a 1/8" reveal

    Work the latch side to a 1/8" reveal

    Close the door. Shim the latch jamb behind the strike location and near the top and bottom until the gap between door and jamb is about 1/8" (3 mm) and the same from top to bottom, and the head gap matches. A nickel is roughly the right thickness to use as a feeler. Tack only — nothing gets set until the swing test passes.

  11. Step 11 of 16

    Check the frame for wind (twist)

    Check the frame for wind (twist)

    Close the door and look at where the door face meets the stop, top and bottom, on both legs. If it touches at the top on one side and at the bottom on the other, the frame is twisted: push the high leg in or out at the top and re-shim before you nail it off.

  12. Step 12 of 16

    The swing test

    The swing test

    Open the door to a quarter, half, and three-quarters and let go each time. It should stay exactly where you left it. Drifting open or shut means the hinge jamb is not plumb — go back to the shims, not the hinges. Do this before you nail anything off: tacks can still come out and shims can still move.

  13. Step 13 of 16

    Nail off the rest of the jamb, then trim the shims

    Nail off the rest of the jamb, then trim the shims

    Only after the swing test passes: drive and set the nails at every shim pair on both legs, then score the shims with a utility knife and snap them flush with the wall. If you use foam, use only low-expansion door and window foam in small beads and let it cure per the label before touching anything.

  14. Step 14 of 16

    Install the lockset and adjust the strike

    Install the lockset and adjust the strike

    Install the lever set you bought for this door per its instructions, then close the door. If the latch does not drop in cleanly, loosen the strike plate and move it a hair, or file the opening slightly — do not fix a latch problem by re-shimming a door that is already plumb.

  15. Step 15 of 16

    Check the bottom gap

    Check the bottom gap

    You want a small, even gap over the finished floor — enough that the door clears carpet, rugs, and the threshold, usually somewhere around 1/2" to 3/4" over the floor for air return. Nothing should drag.

  16. Step 16 of 16

    Quality check before casing

    Quality check before casing

    Everything you do not fix now gets covered by the casing tomorrow. Run the list.

    Quality check

    • Hinge jamb is plumb on the face and on the edge
    • Shim pairs behind every hinge, and one long screw into the framing
    • Reveal is about 1/8" and even across the top and both sides
    • Door stays put at any position — no self-swinging
    • Door face meets the stop evenly: no twist
    • Latch drops in smoothly and the door does not rub
    • Shims trimmed flush; jamb faces flush with the wall

Common mistakes

  • Setting the latch side first, or eyeballing plumb. The hinge jamb carries the whole weight of the door and controls everything. Get it plumb in both directions and dead straight, fasten it, and only then work the latch side to match. If you start anywhere else, the reveal will never come out even. Mistake #1 in this task.
  • Shims anywhere but behind the hinges. A shim pair belongs directly behind every hinge. That is where the load is; without them the jamb flexes, the door sags, and the top corner starts to rub within a month.
  • Driving screws until the jamb bows. Snug, not tight. Over-driven screws suck the jamb toward the stud between shims and put a curve in the hinge side. Check the reveal after every screw and back off if it changes.
  • Regular expanding foam around the jamb. It keeps growing after it looks done and bows the jamb inward, so the door binds. Use only low-expansion door and window foam, in small beads, and leave the shims and the braces in until it cures per the label.
  • A jamb in wind (twisted). Each jamb leg can be plumb and the frame can still be twisted, so the door touches the stop at the top on one side and at the bottom on the other. Close the door and look at the gap along the stop before you nail everything off.
  • Uneven gap between door and jamb. The gap (the reveal) should be about 1/8" and the same all the way around the top and both sides. If it tapers, a shim needs adjusting — fix it now, because casing hides the problem, not the cause.
  • A door that swings itself open or shut. That means the hinge jamb leans. Open the door to a few different positions and let go: it should stay put. If it drifts, the hinge side is not plumb.
Get this job planned for your room

Questions

How long does it take to install a prehung interior door?

Difficulty 3 of 5. For a first-timer, plan on about half a day.

What do I need to install a prehung interior door?

Prehung interior door unit (correct width, height, jamb width, and hand), Composite or cedar shims, 2-1/2" to 3" construction or trim screws (top hinge into the stud), 2-1/2" finish nails (15 or 16 gauge) for the jamb, Low-expansion door and window foam, Passage or privacy lever set (one per replaced door). Tools: 6 ft level (the single most important tool here), Drill/driver, Hammer and nail set, Utility knife (trim shims flush), Wood chisel (only if you have to adjust a hinge mortise), Finish nailer (15/16 ga) with compressor, or cordless.

What are the most common mistakes when you install a prehung interior door?

Setting the latch side first, or eyeballing plumb. The hinge jamb carries the whole weight of the door and controls everything. Get it plumb in both directions and dead straight, fasten it, and only then work the latch side to match. If you start anywhere else, the reveal will never come out even. Mistake #1 in this task. Shims anywhere but behind the hinges. A shim pair belongs directly behind every hinge. That is where the load is; without them the jamb flexes, the door sags, and the top corner starts to rub within a month. Driving screws until the jamb bows. Snug, not tight. Over-driven screws suck the jamb toward the stud between shims and put a curve in the hinge side. Check the reveal after every screw and back off if it changes.

When should I stop and call a pro?

Plumb the hinge side first and shim behind every hinge. A door hung out of plumb never closes right, and the casing hides the fix — so get it right before the casing goes on. Stop and call a carpenter if: the rough opening is too small and would have to be cut wider (framing changes in a load-bearing wall are not DIY); the header or studs are cracked, rotten, or badly bowed; the floor is more than about 1/2" out of level across the opening; or the door is a fire-rated or exterior unit. In a building from before 1978, treat the old painted casing and jamb as lead paint unless a test says otherwise: use lead-safe practices (pry, do not sand, keep it wet, bag the debris), or hire an EPA lead-safe certified firm.